Analysis Shows Home Building Timelines Vary Widely By Region

Have a comment on this article? Share on Facebook!

By John Voket

new_home_construction_single_familyThe National Association of Home Builders recently release an interesting analysis from the 2012 Survey of Construction (SOC).

The raft of data from the Census Bureau shows that on average it takes about 7 months from obtaining a building permit to completing a new single-family home. Looking at the homes completed in 2012, houses built for sale, on average, register the shortest time from permits to completion – between 5 and 6 months.

According to the data, houses built on owner’s land take longer – about 8 months if built by a contractor and more than 11 months if they are owner-built (i.e., where the owner of the land serves as a general contractor). While single-family homes built for rent take, on average, between 8 and 9 months from permits to completion.

For houses built for sale, the SOC also gathers information on sales, registered at the time when a buyer signs a sale agreement or makes a deposit on the home, not the final closing. For new single-family homes sold in 2012, the average time from completion to sale is under one month.

However, this average is highly skewed by a relatively small number of homes that are not sold prior or while under construction, according to the analysis. Looking at new single-family homes completed in 2012, more than three quarters of these properties were sold before or during the completion month, including 30 percent that were pre-sold (i.e., sold before being started).

Only 6 percent of homes completed in 2012 remain unsold as of the first quarter of 2013 the SOC indicates. So, for most new single family homes there is no additional lag from completion to sale.

The time from permits to completion varies across the nine Census divisions with New England and Middle Atlantic regions registering the longer times of between 9 and 10 months.

The Pacific and East North Central division also show above average time of 8 months to completion. Builders in the East South Central Division manage to complete a home in 7 months, on average.

The rest of the country registers times between 5 and 6 months.

Want instant access to great articles like this for your blog or newsletter? Check out our 30-day FREE trial of REsource Licensed Real Estate Content Solutions. Need easy stay-in-touch e-Marketing solutions too? Try Pop-a-Note for 99 cents!
Join RISMedia on Twitter and Facebook to connect with us and share your thoughts on this and other topics.




Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>

Copyright© 2014 RISMedia, The Leader in Real Estate Information Systems and Real Estate News. All Rights Reserved. This material may not be republished without permission from RISMedia.

Content on this website is copyrighted and may not be redistributed without express written permission from RISMedia. Access to RISMedia archives and thousands of articles like this, as well as consumer real estate videos, are available through RISMedia's REsource Licensed Content Solutions. Offering the industry’s most comprehensive and affordable content packages. Click here to learn more! http://resource.rismedia.com

Our Latest News >>